English Commercial Court sets aside an ICC partial award: conflicting arbitration clauses in Tecnicas v PCMC
On 14 July 2025 the Commercial Court held that an ICC tribunal had no jurisdiction because the top-ranking contract document provided for ad hoc arbitration in London. The case is a lesson in drafting dispute clauses across several contract documents.

On 14 July 2025 Bryan J handed down judgment in Tecnicas Reunidas Saudia for Services & Contracting Co Ltd v Petroleum Chemicals and Mining Company Limited ([2025] EWHC 1785 (Comm)). The Commercial Court allowed a challenge under section 67 of the Arbitration Act 1996 and set aside in full an ICC tribunal's partial award on jurisdiction, holding that the tribunal "had, and has, no jurisdiction". The hearing had taken place on 24 June 2025.
The facts and the ruling
The dispute arose from a subcontract for electrochemical works on the Fadhili gas programme in Saudi Arabia, run by Saudi Aramco. Tecnicas was the head contractor and PCMC, described as a Saudi company, was the subcontractor. The subcontract consisted of four documents, and the parties agreed that the Purchase Order listed them in order of precedence: the Purchase Order itself, a Deviation List, technical requisitions and the General Terms and Conditions for Construction Subcontracts (GTCCS).
The documents pointed in different directions. Clause 11.1 of the Purchase Order provided for arbitration in London, in English and under English law, with no reference to any institution or rules. Clause 32 of the GTCCS provided for arbitration administered by the ICC, sitting in Riyadh under Saudi law. Item 18 of the Deviation List recorded English law and London arbitration "under ICC Laws", in wording the judge described as not very skilful.
PCMC began ICC arbitration on 6 October 2023, after the LCIA had declined to initiate an arbitration on 13 September 2023. Tecnicas reserved its position and objected that the only arbitration agreement was an ad hoc one. In a partial award of 18 October 2024 the tribunal found that it had jurisdiction, treating Item 18 as a clear confirmation of ICC arbitration seated in London. Tecnicas challenged that award on 15 November 2024.
The Commercial Court disagreed. It held that the arbitration agreement was clause 11.1 of the Purchase Order, which ranked first, and that, with no rules named, it provided for ad hoc arbitration. The Deviation List recorded negotiating positions rather than contractual terms, and PCMC accepted that it could not alter the Purchase Order. Clause 32 of the GTCCS conflicted with clause 11.1 on seat, governing law and the institution, and the court rejected a "pick and mix" approach that would combine the two. It also held that no prejudice needs to be shown under section 67, because the defect went to the basic architecture of the arbitration, which differs between institutional and ad hoc forms in matters such as appeal rights, appointment of the third arbitrator, oversight and scrutiny of awards.
PCMC argued that Tecnicas had lost its right to object by taking part in the ICC arbitration. The court rejected that argument. Tecnicas had reserved its rights on jurisdiction from the outset, its participation was contingent and precautionary, and the tribunal had itself admitted the objection and ruled on it in a bifurcated phase. The court added that appointing an arbitrator does not bar a later jurisdictional challenge. Tecnicas was therefore not estopped, and had not waived the point.
What it means for contracts and disputes
The following is our analysis of the reported decision. The judgment does not set out drafting lessons as such, but the facts suggest several.
- One dispute clause, not three. Where a contract is built from several documents, each carrying its own dispute resolution wording, the parties should choose one operative clause and state that it prevails over any term in the other documents.
- Name the institution and the rules. A London seat with no rules named is, on this judgment, ad hoc arbitration. If institutional administration is intended, the clause should name the institution and its rules in the document that ranks highest.
- Treat standard terms with care. General terms drafted years earlier for a different purpose may contain a dispute clause that clashes with the negotiated documents. Review them at signing, not at the first dispute.
- Do not rely on negotiation records. A deviation list that records positions as "closed" without amending the operative clause can create exactly the ambiguity that later needs litigating.
The practical cost is also worth noting. The ICC proceedings began in October 2023, and by July 2025 the parties had a partial award that the court set aside. Time and money spent on a tribunal whose jurisdiction is contested can be wasted, and a party that suspects the clause is defective should raise the objection early and expressly reserve its position, as Tecnicas did.
Choosing a forum with a clear clause
The lesson is to settle the forum in one unambiguous clause, with the seat, the rules and the administering body all stated together. GIDI is independent and administers arbitrations under rules the parties choose, whether UNCITRAL, a rule set specified in the contract or a bespoke procedure, and replies to enquiries within 48 hours, so questions about how a clause will operate can be raised before the contract is signed.